Major I-95 Construction Project Set to Begin in North Carolina

1118
I-95 Traffic | I-95 Construction | North Carolina | I-95 Exit Guide

The North Carolina Department of Transportation will start construction later this year on major widening and upgrading one of the oldest sections of Interstate 95, thanks to a federal grant.

The department last year received $147 million in federal funds from the Infrastructure for Rebuilding America program. The INFRA grant was earmarked for widening I-95, and upgrading sections of U.S. 70 to future Interstate 42 in eastern North Carolina. The grant also will pay for the installation of 300 miles of fiber optic cable along both highways to expand access to broadband and telecommunication access.

The Interstate will be widened from four to eight lanes… nearly every interchange and bridge will be rebuilt…

The grant allowed the department to accelerate plans to widen I-95 between exit 56 in Eastover and exit 71 outside Dunn – a 15-mile span in Cumberland and Harnett counties. The interstate will be widened from four to eight lanes.

Nearly every interchange and bridge must be rebuilt to accommodate the wider highway, and meet modern design standards for higher overpasses, wider paved shoulders and longer ramps to enter the freeway. This section of the interstate was built about 60 years ago.

“This is a massive improvement project, and one that is sorely needed,” said Grady Hunt, who represents the Fayetteville area for the N.C. Board of Transportation. “Modernizing the East Coast’s main highway is an important, long-term goal for our state.”

Most of the route does not have a final design yet. The contracting team will finalize the design and coordinate efforts to acquire additional right of way needed for the extra lanes and interchange improvements. The process for completing both will take about a year, although some initial grading around exits 70 and 71 will begin later this year. Construction of the entire project is expected to take about four years to complete.

Although the shoulders will be narrowed for construction, four travel lanes will be maintained during the life of the project. That will mean there will be only brief overnight closures, for example, when bridge girders are set into place over the interstate. In many cases, the existing interchanges or overpasses will remain open to traffic while the new structures are built around the old ones they will replace.

Here are some other project highlights:

  • Pending the final design, 11 bridges will be replaced, including I-95 over the Black River;
  • Service roads would be realigned to allow for I-95 widening and to meet current standards;
  • Roundabouts would be added at some interchanges to minimize impacts to nearby properties, as well as to improve safety and traffic flow;
  • Near Fayetteville at exit 58, a ramp will be built to connect I-95 North traffic going to N.C. 295 South; and
  • The 26-foot median will include inside paved shoulders and a concrete wall separating the direction of travel.

NCDOT currently plans to award a construction contract in July 2020 to widen and modernize I-95 from exit 71 to exit 81, which is the I-40 interchange in Benson.


For more I-95 travel info, visit www.i95exitguide.com, the Internet’s largest and most complete website devoted to America’s Interstate Main Street. Detailed exit service listings… discount lodging, camping, food, gas and more for every exit from Maine to Florida!

Traveling another route? Visit our growing family of exit guides: I-4 Exit GuideI-5 Exit GuideI-10 Exit Guide and I-75 Exit Guide.

I-95 Exit Guide
The I-95 Exit Information Guide is one of the most popular travel destinations on the Internet. This website features detailed listings for exit services all along Interstate 95, from Maine to Florida.